Beta · New Jersey · 564 municipalities · zoning intelligence that stays currentLatest zoning changes
InfinitiZoning
NJ beta
Infiniti Zoning · New Jersey betaFourth Round 2025–2035

Zoning is public, scattered and stale. We make it current, complete and interpreted.

Verified, cited zoning answers for a parcel, and an alert when the rules change. Built for architects, developers, lenders and land-use attorneys, starting with New Jersey's 564 municipalities.

See what changedRead the analysisChange log updated Oct 20, 2026
U.S. zoning jurisdictions
33,295
National Zoning Atlas count
NJ municipalities
564
320 under 10,000 residents
NJ Fourth Round need
80,798
prospective units, DCA Oct 2024
NJ changes logged
57
sourced, Mar 2025 – Oct 2026
High impact
20
change what can be built
U.S. market, base case
≈$298M
a year; range $111M–$620M
Explore

Analysis, monitor and the plan, in one place.

Latest changes

What changed in New Jersey

The five most recent of 57 sourced entries across 31 towns and statewide.

Full change log →
Oct 20, 2026Essex
Maplewood adopts Ordinance 4017-26 making data centers and detention centers non-permitted uses
OrdinanceMaplewood TownshipReportedOrd. 4017-26

The Township Committee gave final approval on October 20 after introducing the ordinance October 6. It amends zoning chapter 271 for every district.

For a site: Neither use can be approved anywhere in Maplewood.

Oct 20, 2026
At least 112 municipalities have adopted data center prohibitions; coalition asks the Governor for a statewide moratorium
OrdinanceStatewideReported

Food & Water Watch's tally reached 112 towns on October 20 with Millburn, Lawrence and Linden voting that night. Hearings were listed for Mahwah and Edison (Oct 26), Stanhope (Oct 27), Hamburg (Nov 2), Bethlehem (Nov 5), Rahway (Nov 9) and Little Egg Harbor (Nov 12). The count is an advocacy figure.

For a site: Roughly one in five New Jersey towns now bars data centers; check the local ordinance before assuming an industrial zone allows one.

Oct 14, 2026Ocean
Jackson introduces Ordinance 20-26-33 tightening warehouse size, setback and buffer limits
OrdinanceJackson TownshipNeeds reviewOrd. 20-26-33

An aggregator summary says the council introduced an ordinance cutting the warehouse size threshold to 50,000 sq ft and requiring 500-foot separation from homes and sensitive uses, now referred to the planning board. The source could not be opened.

For a site: Warehouse proposals in Jackson above 50,000 sq ft or within 500 feet of homes would face new limits if adopted.

Oct 14, 2026Middlesex
Edison introduces an ordinance banning data centers in all zones
OrdinanceEdison TownshipReported

The council voted 7-0 on first reading to amend Chapter 37, adding data centers to the uses prohibited in every zone and removing 'experimental or computation centers' from two permitted-use lists. Facilities of 4 MW per acre or 20 MW overall count regardless of name. Final vote set for October 26.

For a site: Once adopted, no Edison zone will permit a data center, including the industrial corridors.

Oct 13, 2026Essex
West Orange settles the Daughters of Israel builder's remedy suit with a 311-unit retirement community
Affordable housingWest Orange TownshipReported

The council voted 5-0 to approve a settlement allowing a continuing care retirement community at 1155 Pleasant Valley Way: 163 independent living, 84 skilled nursing and 64 assisted living units, seven counted as affordable. A zoning ordinance will follow. A sixth suit over 410 Main Street settled in August.

For a site: The Pleasant Valley Way site will be rezoned for a five-story CCRC; four builder's remedy suits remain against the township.